Saranya Murugesan — Civil Engineer | Digital CV Maker
Senior Electrical Maintenance Engineer

Electrical Site Engineer, 5 yrs

Electrical design engineer with 6 years in commercial and hospital MEP projects across Mumbai and Hyderabad. Prepares HT/LT single-line diagrams, short-circuit and relay coordination studies in ETAP, and DG and transformer sizing.

28Projects delivered
₹340CrBuilt value managed
0Structural NCRs, career
4.2MSafe man-hours led
Project register

Delivered, with dates

Selected projects from the full register of 28. Completion certificates and client references available for every row.

ProjectScaleRoleDelivery
Compressed air and motor efficiency drivereplaced 22 standard motors with IE3 units and fixed air leaks, saving roughly 9 percent on plant electricity
Substation upgradeplanned a weekend shutdown to replace an old VCB panel with zero production loss on Monday

"On time" means the certified completion date, not the press release. One project in 28 ran late — a 2019 mall, 11 weeks, monsoon flooding plus a contractor default. I list it because you'd find it anyway.

Disciplines

What I run on site

Execution & sequencing

Pour cycles, shuttering rotation, crane time, monsoon planning. A tower is a rhythm — my job is keeping the beat when weather, vendors and drawings all miss theirs.

7-day slab cycle held, 8 floors

Quality & QA/QC

Cube registers, rebar inspections, pour cards, NCR closure. Concrete doesn't accept apologies — it accepts cover blocks, vibration and curing, checked every time.

0 structural NCRs in 12 years

Safety leadership

Height work permits, toolbox talks in three languages, and the unpopular decisions — stopping a pour at 4 p.m. because the shoring didn't look right. It wasn't.

4.2M man-hours, 0 fatalities

Contracts & billing

RA bills, BOQ deviations, extra-item claims, subcontractor reconciliation. The technical half wins the site; this half keeps the project solvent.

₹34 Cr claims settled, documented

Planning & MSP

Baseline programmes, look-ahead schedules, catch-up plans that crews actually follow — because they were built with the foremen, not emailed to them.

26 of 28 projects on/ahead

Client & consultant liaison

Weekly reviews, design-query turnaround, the honest flag raised early. Clients renew with engineers whose bad news arrives before it becomes expensive.

3 clients, repeat projects

Site stories

Three days that defined the job

Compressed air and motor efficiency…

replaced 22 standard motors with IE3 units and fixed air leaks, saving roughly 9 percent on plant electricity

Substation upgrade

planned a weekend shutdown to replace an old VCB panel with zero production loss on Monday

SM

Photograph — helmet on, drawings in hand, on the slab

About

Why civil

Electrical engineer with nine years in plant maintenance and projects for automotive component and process plants. Looks after HT and LT distribution up to 11 kV, DG sets, motors, VFDs and PLC-controlled lines.

"The structure will stand for sixty years. The shortcuts would have been invisible for five."

Electrical Supervisor…Certified Energy Auditor…Thermography Level I…

Experience

5 years · current

Senior Electrical Maintenance Engineer

Auto component manufacturer supplying passenger car OEMs

Own electrical upkeep of two machining plants with a connected load of 4.5 MW, two 11 kV substations and 18 DG and UPS systems.

3 years

Electrical Engineer

Electrical contracting firm for industrial and commercial…

Executed electrical installation for three factory buildings, including transformers, LT panels, cable trays, earthing and lighting.

1 year

Graduate Engineer Trainee

Process plant for specialty chemicals

Maintained flameproof motors and lighting fittings in hazardous areas, following permit-to-work and gas testing procedures.

Clients & consultants say

Structural consultant

"Saranya is the only site man who calls me before the problem, not after. The stopped pour in 2022 — his call, against every commercial pressure on that site — is why I take his projects."

Principal, structural consultancy, PuneWorked together on 4 projects

Client project head

"His weekly reports say what's actually happening — including what's late and whose fault it is, his own included. After two decades of contractor optimism, that's worth more than any Gantt chart."

VP Projects, developerRepeat client, 3 projects
Hiring?

Put me on a difficult site

Open to senior electrical maintenance engineer and PMC roles — high-rise, industrial or infrastructure. Pune preferred, site postings anywhere in India considered for the right project. Completion certificates and references ready.

Emailyou@example.comReplies within a day
Phone+00 00000 00000Site hours 7–7 — evenings best
LinkedInlinkedin.com/in/rohitdeshpande-civilProject photos & milestones
RésuméDownload PDFTwo pages + project register
Notice30 days · never mid-pour

✓ Received. You'll hear from me within a day — sites run on follow-through.